01
|
Intersection Improvements at US 45 & Ripley Road, known as Federal Aid Project No. HSIP-0002-07(016) / 106990301 in Prentiss County.
Project Completion: 8/16/2017
|
|
|
1 QandA
|
1
|
|
|
|
|
|
|
02
|
Intersection Improvements at US 61 & Eagles Nest Road, known as Federal Aid Project No. HSIP-0009-06(014) / 106268301 in Coahoma County.
Project Completion: 9/29/2017
|
|
|
1
|
1
|
|
|
|
|
|
|
03
|
Median Barrier Installation on US 278/SR 6 from Jackson Avenue to University Avenue, & SR 7 approximately .3 miles north of the Belk Blvd. Intersection and north to the 4-lane past SR 30/Molly Barr, known as Federal Aid Project No. HSIP-0070-04(023) / 107109301 in Lafayette County.
Project Completion: 3/16/2018
|
|
|
1 QandA
|
1
|
|
|
|
|
|
|
04
|
Intersection Improvements on US 45 at Pratt, Fashion Way and SW Avenue, known as Federal Aid Project No. NHPP-0002-06(022) / 107209301 in Lee County.
Project Completion: 10/18/2017
|
|
|
1 2 QandA
|
1 2
|
|
|
|
|
|
|
05
|
Mill & Overlay of US 80 from Terry Road to East of Bierdeman Road, & US 51 from RR to Town Creek, known as Federal Aid Project Nos. NH-7314-00(028) / 107187301, 302, & NH-6928-00(012) / 107187303 in Hinds & Rankin Counties.
Project Completion: 8/9/2017
|
|
|
1 QandA
|
1
|
|
|
|
|
|
|
06
|
Raised Pavement Markers on various routes in District (3), known as State Project No. MP-3000-00(107) / 305941301 Districtwide.
Project Completion: 3/31/2017
|
|
|
|
|
|
|
|
|
|
|
07
|
Construction of Byhalia Bulk Salt Storage Structure, known as State Project No. BWO-2218-47(001) / 503020301 in Marshall County.
Project Completion: 6/30/2017
|
|
|
QandA
|
|
|
|
|
|
|
|